Visual Arts Building Photo Gallery
Jun 16, 2008
 |
 |
| Contractors begin the process of readying the ground for sidewalks. |
The entrance of the building is nearly
complete with all windows and doors
installed.
|
 |
|
| The exterior brick is finished and shows off the building’s progress. |
|
May 9, 2008
 |
 |
| Contractors lay brick on the South side of the building in mid April. |
Cabinets are installed in studios throughout the building. |
 |
|
| The interior comes together with the addition of paint throughout.
|
|
April 11, 2008
 |
 |
| Contractors begin laying brick on the north side of the building in late March. |
Tile is installed in the
first floor bathrooms.
|
 |
|
| Interior windows are installed throughout the building. |
|
March 17, 2008
 |
 |
| With the sheetrock installed, interior windows and doorways are framed. |
Contractors begin installation of the elevator in early February. |
 |
|
| Doors and windows are installed at the building’s main entrance. |
|
Feb. 8, 2008
 |
 |
| The layout of the interior becomes evident through the framing of rooms. |
Insulation and sheetrock go up in the hallway and classrooms. |
 |
|
| Despite the heavy snowfall, the next step of roofing is complete and exterior windows are installed. |
|
Jan. 3, 2008
 |
 |
| The completion of the roof shows off the building's progress. |
Installation of exterior insulation board is nearly complete. |
 |
|
| Concrete is poured throughout the building. |
|
Dec. 5, 2007
 |
 |
| The installation of steel beams gives basic structure to the outer walls. |
The doors and windows become evident through the installation of exterior insulation board. |
 |
|
| Interior heating systems are being installed. |
|
Nov. 5, 2007
 |
 |
| The roof begins to take shape with the addition of aluminum panels. |
The pouring of concrete gives definite shape to the first floor interior. |
 |
|
| The artistic shape of the building comes out with the eastern side of the roof. |
|
Oct. 10, 2007
 |
 |
| The buildings three dimensional structure takes shape through the installation of steel framing. |
The two stories of the building are now separated by the initial layers of flooring. |
 |
|
| The second floor interior layout is becoming evident. |
|
Sept. 4, 2007
 |
 |
| During the month of August work focused on pouring the vertical concrete walls. |
With these walls the building can be seen more easily from
the loop |
Aug. 3, 2007
 |
 |
| The building foundation began to take form at the end of July. |
On Aug. 1 concrete was poured for the foundation. |
 |
|
| By Aug. 3 the outline of the building was established. |
|
July 11, 2007
 |
 |
| June consisted of setup work on the underground utilities. |
Excavation began early July to prepare for the building foundation. |
 |
|
| The parking and roadway behind the site have begun to take shape, as well as the building site itself. |
|
|
|